Update 08/03/2024: Due to the wet weather conditions expected next week the road resealing crew will be taking a break. They will be completing Richmond Street in Cobden today and then will return to complete the programme week commencing 18 March.
-----------------------------------------------------------------------------------------------------
When the weather settles, our roading crews will be out and about the streets in Greymouth sealing roads. ⛅🌤🌞
If your street is affected, you should have received a notice in your letterbox. 📫
The work is weather dependent so may change at short notice. We'll update this page with any changes to the planned works.
As always, please be careful around work sites and take note of the signs.🛑🦺😃👍
Programme of work
Wednesday 28 February
- Elizabeth Street - Complete
- Eva Street - complete
- Sinnot Road - complete
- Byron Triangle Street - complete
Thursday 29 February
- Heaphy Street - complete
- Preston Road - complete
- Swift Street - complete
- Achilles Triangle Road - complete
Friday 1 March
Tuesday 5 March
- Sumner Road - complete
- Tasman St - complete
- Byron Street - complete
- Winnie Street - complete
- Puketahi Street - complete
- Murray Street East - complete
Wednesday 6 March
- Water Walk Road - complete
- Felix Campbell Street - complete
- Arney Street - complete
- Richmond Quay -complete
Thursday 7 March
- Marlborough Steet - complete
- Turumaha Street - complete
- Thompson Street - complete
- Domain Terrace - complete
- Joyce Crescent - complete
Friday 8 March
- Clifford Street 2 - complete
- Clifford Street 1 - complete
- Richmond Street - complete