Our building and planning team will continue processing consent applications right up until 24 December 2026. However, please note that the official “working day count” on applications will pause over the holiday period.
The Building Act 2004 and the Resource Management Act 1991 state that the period between 20 December and 10 January each year is excluded from the 'working days count' for all timeframes. This means that any weekdays during this period will not be counted as working days.
Building Inspections
- Inspections will be carried out until 5pm, Monday 21 December 2026.
- To avoid delays, please book early rather than leaving it to the last minute.
- Bookings will reopen from Tuesday 5 January 2027.
LIM Applications
To ensure a LIM is completed before Christmas, the application needs to be submitted on or before Wednesday, 9 December 2026.